ROVER PIPELINE
Energy Transfer
is the parent company of the Rover
Pipeline. Rover can also be
contacted at 1-888-844-3718. When you
call, leave a message and they will return your call within 24 hours.
Proposed Timeline:
Rover Submits FERC Pre-Filing Request - June 2014
Project Open Houses Conducted Along Route
- July and September 2014
FERC Scoping Meetings Held Along Route
- November and December 2014
Rover Files FERC Certificate Application
- February 2015
FERC Issues Certificate Anticipated
- November 2015
FERC Issues Construction Authorization
- January 2016
In Service to Midwest Hub - December 2016
In Service to Market Zone North - June 2017
NEXUS PIPELINE
DTE Energy and Spectra Energy are the Lead Developers of the Nexus Pipeline. General information about how this project
may involve your property can be directed to 1-877-589-3655.
UTOPIA EAST PROJECT
Kinder
Morgan is the parent company behind the Utopia
East project. Questions can be
directed to Karen Kabin at Karen_Kabin@kindermorgan.com
or by calling 719-369-9268.
Estimated Timeline:
Stakeholder outreach – Ongoing
Begin survey activities in the field – May 2015
Begin construction – November 2016
Project is placed in service – January 2018
Additional Points of Reference:
Additional considerations to ask about:
• Get everything written into easement agreement
• Topsoil---loss and value associated with loss or replacement
• Years of production loss
• Subsurface drainage re-install in right-of-way after all settling complete
• Abandoned oil wells—sealed and closed to standards
• Cover on pipeline 2’ or greater in relation to deepest drain tile
• Parallel right-of-way with header mains
• Pump drainage install and additional yearly operating costs
• Value of property in future years….development and or lack thereof
• Repairing drainage in future years because of maintenance
• Stone and rock---remove, crush on site
• Cleanup of right-of-way no debris larger than 4”
• Increased Radon Gas levels
• Noise from product movement and compression. Hearing loss from prolonged exposure
• Stray voltage due to electric charge on pipeline
• Only product “X” in line
• Monitoring devices in fence rows or road right of ways—not in crop fields
• No above ground devices (anything to farm around)
• Excess soil from pipe displacement
• 24 -7 access to each side of construction easement as pipeline crosses property
Wood SWCD does not have the ability to review or block pipelines. It is up to the land owner to hire an attorney if you think you need one.